Episode 111 ~2:00 Power

ETAP for MV/LV

Load flow, short circuit, arc flash, protection coordination, the four studies every MV/LV project hands the consultant, all from one model and one source of cable and transformer data.

Animated explainer, press play to watch the concepts now; the filmed cut publishes once production wraps.

What you'll walk away with

01

Single model, four studies.

Build the SLD once with cable and transformer data. ETAP runs load flow, fault currents, arc flash, and TCC coordination from the same model, no duplicate inputs.

02

Load flow shows voltage drop and losses.

IEC 60364 limits voltage drop at 4% at the final circuit. ETAP highlights buses exceeding the limit in red. Transformer tap settings come out of this study, not a guess.

03

Arc flash incident energy → PPE category.

Output is cal/cm² at each bus. Above 8 cal/cm² needs Category 3 PPE. Saudi MV substations almost always exceed this on the line side, the study tells you where.

04

Selectivity is where systems live or die.

A single fault should trip one breaker, not the whole feeder. TCC plots show curves overlapping. Re-grade the upstream relay or change the fuse, then re-run the study.

ETAP analyses × what each one tells you

The studies that have to land before commissioning.

StudyOutputUsed for
Load flowVoltage drop %, kW lossesCable + transformer sizing
Short-circuitIsc kA, X/RSwitchgear breaking capacity
Protection coordinationTime-current curvesSelectivity, arc reduction
Arc-flashIncident energy cal/cm²PPE category, labels
Harmonic analysisTHDi %, IHDi per nodeFilter / transformer K-rating
Motor startingVoltage dip, torque vs speedDOL vs VSD decision
Reliability assessmentSAIFI, SAIDI, ECOSTCritical-power architecture

Five decisions that ride on the ETAP model

ETAP is the SLD that knows physics. Build it once, study it five times.

Library accuracy is everything.

Use vendor-supplied .etap libraries for Schneider, ABB and Siemens transformers, breakers and motors. Generic IEC defaults are off by 5-15% for impedance, enough to mis-size a breaker.

Load flow at 100% load is the easy case.

Run 110% load, 90% voltage, summer / winter, and motor-starting transient. Saudi grid voltage swings 0.95-1.05 pu typical; design for the worst-case combination, not nameplate.

Short-circuit drives every breaker spec.

IEC 60909 Isc at every bus, then check each breaker's Icu and Ics against the calculated kA. Above the published Icu and the breaker explodes on a fault, a real and ongoing problem with imported gear.

Arc-flash labels are mandatory on every panel ≥ 50 V.

IEEE 1584-2018 / NFPA 70E calculates incident energy and arc-flash boundary; the label states PPE category. Saudi LOTO regimes increasingly require these, install them in the build, not after the incident.

Protection coordination is study + commissioning, not just study.

The ETAP curves drive relay settings; commissioning verifies them with primary injection. A curve that's selective on paper but un-commissioned trips the upstream breaker on every downstream fault.

Next Episode

KNX ETS5

Watch next

Get the next episode by email

Practical lighting know-how from NLC Academy. No spam, unsubscribe anytime.

By subscribing you agree to receive NLC emails.