Episode 41 ~2:10 Saudi-Specific EN · العربية

The Saudi MV
tariff & SEC interface

The Saudi Electricity Company supplies most commercial and industrial loads at medium voltage. But where does SEC's responsibility end and yours begin? Who owns the transformer? Who pays for the protection? The MV interface decisions made at design lock in 25 years of operating cost.

Animated explainer, press play to watch the concepts now; the filmed cut publishes once production wraps.

What you'll walk away with

Four ideas to carry into the next specification conversation you have.

01

MV ownership boundary = the demarcation.

Up to the supply transformer secondary: SEC. From there: customer. Some sites (large industrial) own the transformer too, pays for itself in tariff savings.

02

Tariffs are kWh + kVA + reactive.

kWh = energy consumed. kVA = peak demand (15-min average). kVARh = reactive penalty if pF below threshold.

03

Industrial tariff bands depend on contract demand.

100 kVA, 500 kVA, 1 MVA, 10 MVA, each threshold has different unit prices and demand structure. Pre-design the contract demand carefully.

04

Time-of-use windows reward off-peak.

Peak afternoon (1-5 PM, Saudi summer) is most expensive. Mid-night base loads can be 60% the daytime rate. EV charging and data centre cooling are big TOU optimisers.

Saudi MV supply voltages × purpose

SEC standard MV distribution voltages.

Voltage Typical use Ownership / interface
400 V LVSmall commercial, residentialSEC up to meter
13.8 kV MVStandard commercial / light industrySEC to transformer secondary
33 kV MVLarge industrial, district coolingSEC to dedicated substation
132 kV HV (sub-trans)Mega-projects (NEOM, Aramco, big malls)Dedicated step-down at customer
380 kV HV (transmission)Major industrial cities, IPPDirect interconnection agreement

Designing the MV interface

Five decisions that shape 25 years of operating cost.

Customer-owned transformer vs SEC-owned.

SEC-owned: simpler, lower upfront cost, you pay LV tariff. Customer-owned: higher upfront, you pay MV tariff (lower per kWh), you maintain the transformer. Crossover typically at ~500 kVA continuous load.

Contract demand is a 12-month commitment.

The kVA you declare to SEC sets your monthly fixed charge. Declare too high = paying for unused capacity. Declare too low = penalty surcharge if you exceed. Audit historical demand before declaring.

Power factor below 0.85 triggers reactive billing.

kVARh meter records reactive energy. Industrial tariffs charge for it above the pF threshold. APFC bank payback typically 12-24 months on any commercial site with motor loads.

Time-of-use rates change project economics.

Saudi summer afternoon peak (13:00-17:00) is the most expensive hour. Pre-cooling thermal mass, scheduling EV charging at 22:00-06:00, and running data-centre cooling at off-peak can cut electricity costs 15-30%.

SEC requires standardised interconnection equipment.

Saudi grid code mandates specific protection relays, metering classes (Class 0.5S), and disconnect arrangements at the MV interface. Use SEC-approved nameplates only. Non-compliance delays energisation by months.

Next Episode

K-Factor Transformers

Watch next

Get the next episode by email

Practical lighting know-how from NLC Academy. No spam, unsubscribe anytime.

By subscribing you agree to receive NLC emails.